Wallbrook - Under Review

This webpage contains all the Development Applications that are currently Submitted and Under Review by the Town Technical Review Committee and/or Town Planning Board/Board of Commissioners (depending on the type of application).  Once an Application achieves its final Approval, those records will be moved to the "Wallbrook - Approvals" webpage.


SDP-23-04 - UNDER REVIEW - Site Development Plan of Lot 11 of the Wallbrook commercial development for a 7-Eleven convenience store/gas station .

  • 1st Submittal Received 05-01-23 - Comments published on 05/25/2023.
  • 2nd Submittal received 06/01/2023; on TRC-STAFF review during JUNE 2023; Comments published on 06-23-2023.   
  • 3rd Submittal received 03/01/2024; on TRC-STAFF review during MARCH 2024; Comments published on 04-05-2024. 

  -- Wake Co. Permit SEC-119905-2024/SWF-119905-2024 Disapproval dated 4-5-2024. 

  • 4th Submittal received 05/01/2024; on TRC-STAFF review during MAY 2024; Comments published on 06-09-2024. 
  • 5th Submittal received 09/13/2024; on TRC-STAFF review during OCTOBER 2024; Comments publised on 10-15-2024.

-- Wake Co. Permit SEC-119905-2024/SWF-119905-2024 Disapproval dated 9-26-2024. 

CID-23-04 - UNDER REVIEW - Construction Infrastructure Drawings for the (north/west side of S. Main Street) extension of Virginia Water Drive (as a cul-de-sac street).

  • 1st Submittal Received 05-01-23 - Comments published on 05/25/2023.
  • 2nd Submittal received 06/01/2023; on TRC-STAFF review during JUNE 2023; Comments published on 06/23/2023. 
  • 3rd Submittal received 03/01/2024; on TRC-STAFF review during MARCH 2024; Comments published on 04/06/2024.  
  • 4th Submittal received 05/02/2024; on TRC-STAFF review during MAY 2024; Comments published on 06/09/2024. 
  • 5th Submittal received 09/13/2024; on TRC-STAFF review during OCTOBER 2024; Comments published on 10/14/2024

 

CID-24-02 - UNDER REVIEW - Construction Infrastructure Drawings for Lot 7, for mass grading and erosion control purposes.  This application is submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 04-01-2024, on review during APRIL 2024; Comments published 05/01/2024. 

- 2nd Submittal rcvd 06-04-2024, on review during JUNE 2024; Comments published 06/21/2024.  

- 3rd Submittal rcvd 07-01-2024, on review during JULY 2024; Comments published 07/17/2024.  

   - TRC Review is complete; Wake County SEC-121765-2024 approval required by/before signatures.

  - 2024-10-02 - Wake County Permit SEC-121765-2024 DISAPPROVAL Letter issued.

 

CID-24-03 - UNDER REVIEW - Construction Infrastructure Drawings for Lot 8, for mass grading and erosion control purposes. This application is submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 04-01-2024, on review during APRIL 2024; Comments published 05/01/2024.  

- 2nd Submittal rcvd 06-04-2024, on review during JUNE 2024; Comments published 06/21/2024.  

- 3rd Submittal rcvd 07-01-2024, on review during JULY 2024; Comments published 07/17/2024.  

   - TRC Review is complete; Wake County SEC-121766-2024 approval required by/before signatures.

SDP-24-03 - Chase Bank Wallbrook - UNDER REVIEW -  Site Development of (currently proposed Lot 5A per PSP-24-01 and FSP-24-13) for a commercial bank office.

- 1st Submittal rcvd 04-29-2024, on review during MAY 2024; Comments published on 06/09/2024.

- 2nd Submittal rcvd 07-01-2024, on review during JULY 2024; Comments published on  08/01/2024.

FSP-24-13 - Wallbrook Lots 5A,5B,5C,5D - UNDER REVIEW - Final Subdivision Plat to divide 6.48 acres, being PIN 1758563963 (Lot 5 of PR 21-04 Revised) into 4 non-residential lots.

  • 1st Submittal rcvd 2024-09-03; on TRC Staff review during SEPTEMBER 2024; comments published on 2024-09-23.
  • 2nd Submittal rcvd 2024-10-03; on TRC Staff review during OCTOBER 2024; comments published on 2024-10-15.

 

FSP-24-16 - Townhomes - UNDER REVIEW - Final Subdivision Plat to divide __XXX_ acres of the planned 24.28 acres, being PIN 1758569725 (Lot 6 of PR 21-04 Revised) into XXX single-family attached (townhome) residential lots and xxxxxxxxx.  This is the Phase 1 of two planned Phases for the townhome subdivision.

  • 1st Submittal rcvd 2024-08-26; on TRC Staff review during SEPTEMBER 2024; comments published on 2024-10-04
  • 2nd Submittal rcvd 2024-10-31; on TRC Staff review during NOVEMBER 2024; comments to be published by/on 2024-12-09

 

SDP-24-07 - Fifth/Third Bank Wallbrook - UNDER REVIEW - Site Development of (Lot 3 per FSP-24-09, BM2024/Pg1692-1693) for a commercial bank office. V1 Plans are 21 sheets.

  • 1st Submittal rcvd 08-29-2024, on review during SEPTEMBER 2024; Comments published on 2024/10/04.
  • 2nd Submittal rcvd 10-30-2024, on review during NOVEMBER 2024; Comments to be published by/on 2024/12/09.

 

PSP-24-06 - Wallbrook Lot 8 - UNDER REVIEW - Preliminary Subdivision Plat to subdivide Lot 8 (*recorded lot via BM2023/PG1600-1602, aka FSP-23-09), being 5.33 acres, into 2 lots (8A, being 2.93 acres & 8B, being 2.40 acres), more TBD.

  • 1st Submittal rcvd 2024-09-03; on TRC Staff review during SEPTEMBER 2024; comments published on 2024-10-04. 
  • 2nd Submittal rcvd 2024-11-03; on TRC Staff review during NOVEMBER 2024; comments published on 2024-11-22.

 

SP 22-09 REVISION - Wallbrook Townhome Amenity Center - UNDER REVIEW - Revision to the previously approved SP 22-09 for an amenity center site within this townhome subdivision.

  • 1st Submittal rcvd 2024-09-03; on TRC Staff review during SEPTEMBER 2024; comments published on 2024-09-18

 

CD 22-04 REVISION - Wallbrook Townhome Construction Drawings - UNDER REVIEW - Revision to the previously approved CD 22-04 for the infrastructure related to this townhome subdivision, pursuant to SP 21-02 (Preliminary subdivision plat for 140 townhome lots etc).  

The V1 submittal consists of 14 Sheets, being: C.00 (Project Notes);  C2.00 (Overall Site Plan);  C2.01 (Site PLan-Area A);  C2.02 (Site Plan-Area B);  C9.A1 (Stormwater Control Measure "A" Plan View);  C9.A2 (Stormwater Control Measure "A" Details);  C9.A3 (Stormwater Control Measure "A" Details);  C9.A4 (Stormwater Control Measure "A" Landscape Plan);   C9.B1 (Stormwater Control Measure "B" Plan View);    C9.B2 (Stormwater Control Measure "B" Details);  C9.B3 (Stormwater Control Measure "B" Details);   C9.B4 (Stormwater Control Measure "B" Landscape Plan);  L5.00 (Overall Code Landscape Plan);  L5.01 (Enlarged Code Landscape Plan). 

  • 1st Submittal rcvd 2024-09-03; on TRC Staff review during SEPTEMBER 2024; comments to be published by/on 2024-09-13.
  • 2nd
  •  

SDP-24-09 - UNDER REVIEW - Site Development Plan of Lot 8A of the Wallbrook commercial development for a ______  .

  • 1st Submittal Expected DECEMBER...

FSP-24-22 - UNDER REVIEW  - Final Subdivision Plat to record lots 1A, 1B, 1C, and 2 from Revised PR 21-04; these 4 lots are presently recorded as "Tract B" in BM2023/Pg1600-1602.

  • 1st Submittal Expected DECEMBER...

Documents

CID-24-02 - Lot 7 - Wake Co Permit Disapproval 10-02-2024

SP 22-09 REVISION - Wallbrook Townhome Amenity Center - V1

SDP-24-09 - Wallbrook Lot 8A - V1 Expected December ????

FSP-24-22 - Wallbrook Lot 8A - V1 Expected December ????