Wallbrook - Under Review

This webpage contains all the Development Applications that are currently Submitted and Under Review by the Town Technical Review Committee and/or Town Planning Board/Board of Commissioners (depending on the type of application).  Once an Application achieves its final Approval, those records will be moved to the "Wallbrook - Approvals" webpage.


 

CD 22-02 REVISION - A Revision to the previously approved Construction Drawings for mass grading & sewer line realignmentThis application is regulated under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 02-01-2023 - Comments published 03/06/2023.  Awaiting a Resubmittal.

CID-23-01 - Construction Infrastructure Drawings for Roadway Improvements including Wallbrook Drive and Virginia Water Drive within the Wallbrook subdivision. This application was submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 02-01-2023  - Comments published 03/06/2023.

- 2nd Submittal rcvd 06-23-23 - on TRC-STAFF Review during July, comments published on 07/27/2023.

CID-23-02 - Construction Infrastructure Drawings for Lots 1A, 1B, 1C, and 2 within the Wallbrook subdivision. This includes 3 lots for retail/commercial uses (incl. Publix) and the primary stormwater control measure (pond). Original CD Plan set file over 100KB, is broken into 4 parts to allow uploading to Town webpage. This application was submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 03-03-2023 - Comments published 04/05/2023.   Awaiting a Resubmittal.

SP 22-03 REVISION - Site Plan for Lots 1A, 1B, 1C, and 2 from REVISED PR 21-04, to construct Buildings 1,2,3,4 including PUBLIX.  This application was submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 03-03-2023 - Comments published 03/30/2023.   Awaiting a Resubmittal.

SDP-23-04 - Site Development Plan of Lot 11 of the Wallbrook commercial development for a 7-Eleven convenience store/gas station .

- 1st Submittal Received 05-01-23 - Comments published on 05/25/2023.

- 2nd Submittal received 06/01/2023; on TRC-STAFF review during JUNE 2023; Comments published on 06-23-2023.   

- 3rd Submittal received 03/01/2024; on TRC-STAFF review during MARCH 2024; Comments published on 04-05-2024. 

  -- Wake Co. Permit SEC-119905-2024/SWF-119905-2024 Disapproval dated 4-5-2024. 

- 4th Submittal received 05/01/2024; on TRC-STAFF review during MAY 2024; Comments published on 06-09-2024. 

CID-23-04 - Construction Infrastructure Drawings for the (north/west side of S. Main Street) extension of Virginia Water Drive (as a cul-de-sac street).

- 1st Submittal Received 05-01-23 - Comments published on 05/25/2023.

- 2nd Submittal received 06/01/2023; on TRC-STAFF review during JUNE 2023; Comments published on 06/23/2023.  

- 3rd Submittal received 03/01/2024; on TRC-STAFF review during MARCH 2024; Comments published on 04/06/2024.  

- 4th Submittal received 05/02/2024; on TRC-STAFF review during MAY 2024; Comments published on 06/09/2024

 

 

MOVE TO APPROVED ----  SDP-23-05 - Site Development Plan + Construction Infrastructure Drawings for Lots 1A, 1B, 1C, 2, and 3 (portion) for development of Publix grocery store building, 3 other retail buildings, parking lots and landscaping, and infrastructure including stormwater control measure to serve this development.  * Submittal combines SDP-23-05 and CID-23-01, Construction Drawings for the 2 public roadways in the subdivision (Virginia Water Drive and Wallbrook Drive).  Plans should be reviewed as one single plan set of both on-lot site development and associated off-site public infrastructure construction.

 

PSP-24-01 - Wallbrook Lot 5 (Boat Tract) - Preliminary Subdivision Plat of Lot 5 per PR 21-04 and FSP-23-09 into 4 lots (xxxxx)

- 1st Submittal received 04/01/2024; on TRC-STAFF review during APRIL 2024; Comments published on 05/02/2024.  

- 2nd Submittal received 06/04/2024; on TRC-STAFF review during JUNE 2024; Comments published on 06/21/2024

CID-24-02 - Construction Infrastructure Drawings for Lot 7, for mass grading and erosion control purposes.  his application is submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 04-01-2024, on review during APRIL 2024; Comments published 05/01/2024

- 2nd Submittal rcvd 06-04-2024, on review during JUNE 2024; Comments published 06/21/2024.  

CID-24-03 - Construction Infrastructure Drawings for Lot 8, for mass grading and erosion control purposes. This application is submitted/reviewed/Approved under the Land Development Ordinance (LDO). 

- 1st Submittal rcvd 04-01-2024, on review during APRIL 2024; Comments published 05/01/2024.  

- 2nd Submittal rcvd 06-04-2024, on review during JUNE 2024; Comments published 06/21/2024.  

 

FSP-24-09 - Wallbrook Tract A (Lots 3 & 4) - Final Subdivision Plat to record lots 3 and 4 pursuant to PR 21-04 and FSP-23-09.

- 1st Submittal rcvd 04-04-2024, on review during MAY 2024; Comments published on 06/01/2024.

- 2nd Submittal rcvd 06-28-2024, on review during JULY 2024; Comments published on ___tbd___/2024.

SDP-24-03 - Chase Bank Wallbrook - Site Development of (currently proposed Lot 5A per PSP-24-01) for a commercial bank office.

- 1st Submittal rcvd 04-29-2024, on review during MAY 2024; Comments published on 06/09/2024.